Three Scenarios

The estimate range reflects unknowns — soil conditions, tree density, and drainage — that site investigation will resolve.

Optimistic
$48,000
$69 / LF
Better soils (CBR>5), lighter woods, owner clears trees, 2 culverts, 10% contingency
Expected
$71,700
$102 / LF
Clay subgrade, heavy woods, 8" base, 3 culverts, 15% contingency as estimated
Conservative
$93,500
$134 / LF
Worst soils (CBR<3, 12" base), very heavy timber, wetland found, 25% contingency
$48,000 $93,500
Optimistic Expected $71,700 Conservative

Breakdown by Category

Where the money goes. Base and surface aggregate account for nearly a third of direct costs.

Base & Surface
32% $20,044
General Conditions
19% $12,000
Clearing & Grubbing
16% $10,152
Drainage
16% $9,880
Earthwork
9% $5,864
Finish Work
7% $4,400
Contingency
15% $9,351
Direct Cost
$62,340
+
Contingency (15%)
$9,351
=
Estimated Total
$71,691

Line Items

Expand each section to see individual pay items, quantities, and unit prices. All prices include labor, equipment, materials, overhead, and profit.

1.0 General Conditions $12,000
ItemUnitQtyUnit PriceTotal
1.1 Mobilization / DemobilizationLS1$4,500$4,500
1.2 Surveying & StakingLS1$2,500$2,500
1.3 Erosion Control (Temporary)LS1$3,000$3,000
1.4 Traffic Control (approach work)LS1$500$500
1.5 Permits & FeesLS1$1,500$1,500
Subtotal 1.0$12,000
Mobilization covers equipment transport for a small project. Erosion control includes ~300 LF silt fence, straw wattles at drainage points, and a stabilized construction entrance at Cerro Gordo Rd. Permits assume Lane County approach permit ($500–$1,500); no DEQ 1200-C (under 1 acre). Oregon 811 locate is free.
2.0 Clearing & Grubbing $10,152
ItemUnitQtyUnit PriceTotal
2.1 Clear & grub (heavy woods)ACRE0.51$16,000$8,160
2.2 Strip topsoil (6")CY207$6.00$1,242
2.3 Dispose of slash/debrisCY150$10.00$1,500
2.4 Timber credit (salvage)LS1($750)($750)
Subtotal 2.0$10,152
Heavy woods at $16,000/acre is mid-range for second-growth Douglas fir. Timber credit assumes 1–2 MBF salvaged; could be $0 to $2,000+ depending on tree size and mill demand. Potential savings: If the landowner handles tree removal, clearing cost drops significantly.
3.0 Earthwork $5,864
ItemUnitQtyUnit PriceTotal
3.1 Excavation (smooth undulations)CY100$12.00$1,200
3.2 Fill placement & compactionCY50$9.00$450
3.3 Subgrade preparationSY1,004$3.50$3,514
3.4 Proof-rollLF700$1.00$700
Subtotal 3.0$5,864
Earthwork is minimal given the gently undulating terrain. Subgrade prep includes shaping 3–4% crown, moisture conditioning, and compaction. Proof-roll with a loaded dump truck identifies soft spots. If soft spots are found, over-excavation adds ~$15/CY.
4.0 Drainage $9,880
ItemUnitQtyUnit PriceTotal
4.1 18" CMP cross-drain culvertsLF72$40.00$2,880
4.2 Culvert end sections (metal)EA6$275.00$1,650
4.3 Ditch excavation (V-ditch, uphill)LF700$5.50$3,850
4.4 Rock check damsEA4$275.00$1,100
4.5 Rip-rap (outlet protection)CY5$80.00$400
Subtotal 4.0$9,880
Three cross-drain culverts at low points, each 24 LF. 18" CMP is minimum; upgrading to 24" preferred for maintenance access would add ~$720–$1,800. Ditch on uphill side only; if terrain requires both sides, add ~$3,850. Check dams where ditch grade exceeds 3%.
5.0 Base Course $14,896
ItemUnitQtyUnit PriceTotal
5.1 Geotextile separation (non-woven)SY1,351$2.25$3,040
5.2 Aggregate base — delivered (3/4" minus)TON312$32.00$9,984
5.3 Aggregate base — place & compactTON312$6.00$1,872
Subtotal 5.0$14,896
8" aggregate base placed in two 4" lifts, each compacted. Thickness based on assumed CBR < 5. If borings show CBR > 5, base could reduce to 6" (saving ~$3,000). Delivered price assumes ~10 mile haul from Cottage Grove area quarry. Includes quantities for two 40×8 ft passing turnouts.
6.0 Surface Course $5,148
ItemUnitQtyUnit PriceTotal
6.1 Surface aggregate — delivered (3/4" minus)TON117$38.00$4,446
6.2 Surface aggregate — place & compactTON117$6.00$702
Subtotal 6.0$5,148
3" surface course of well-graded 3/4" minus crushed rock. Higher unit price than base due to tighter gradation spec. Surface aggregate should have adequate fines (5–10% passing #200) for binding without becoming muddy.
7.0 Finish Work $4,400
ItemUnitQtyUnit PriceTotal
7.1 Shoulder gradingLF1,400$1.50$2,100
7.2 Permanent erosion controlLS1$1,200$1,200
7.3 Seeding & mulchingACRE0.35$1,000$350
7.4 Signage & delineationLS1$250$250
7.5 Final cleanupLS1$500$500
Subtotal 7.0$4,400
Shoulder grading on both sides, blending into existing terrain. Seeding uses native seed mix per conservation easement requirements (may be specified by land trust). Permanent erosion control converts temporary BMPs and stabilizes all disturbed slopes.

Key Quantities

Material and area quantities derived from the 700 ft × 12 ft road prism with 32 ft clearing width and two passing turnouts.

Clearing & Earthwork

Clearing width32 ft
Clearing area0.51 ac
Road prism width20 ft
Topsoil stripping207 CY
Cut volume100 CY
Fill volume50 CY

Aggregate & Fabric

Geotextile1,351 SY
Base aggregate (8")312 tons
Surface aggregate (3")117 tons
Total aggregate429 tons
Estimated truckloads~22

Drainage

Cross-drain culverts72 LF
Culvert end sections6 EA
Ditch length700 LF
Check dams4 EA
Rip-rap5 CY

Design Parameters

Crown slope3–4%
Assumed subgrade CBR3–6
Base thickness8 in
Surface thickness3 in
Passing turnouts2
Turnout size40×8 ft

Potential Savings

Opportunities to reduce cost, totaling $13,000–$23,000 if all are realized.

Savings Opportunities

Owner-performed clearing$5K–$8K
Timber salvage credit$0.5K–$2K
Better soils (CBR>5)$3K–$5K
Combine w/ nearby work$2K–$4K
Owner hires surveyor$2K–$2.5K
Burn slash on-site$0.5K–$1K

Add-Alternates

Chip seal surface+$7K–$10K
2" HMA (asphalt) surface+$14K–$19K
Third passing turnout+$1.5K–$2K
Dust palliative (MgCl)+$1.5K–$2.8K
Gate at road entrance+$1K–$3K

Construction Timeline

Estimated 5–9 working days during the June–September dry season window.

Phase Duration

Pre-construction (survey, erosion control, 811)1 day
Clearing & grubbing1–2 days
Earthwork & subgrade1–2 days
Drainage (culverts & ditch)0.5–1 day
Base & surface aggregate1–2 days
Finish (shoulders, seed, cleanup)0.5–1 day
Total5–9 days

Key Assumptions

This estimate will be refined as site investigation data becomes available. Items marked with risk are the primary sources of cost uncertainty.

  1. Clay subgrade assumed (Jory/Bellpine series), CBR 3–6 wet. No site-specific borings yet.
  2. 8" base + 3" surface over geotextile. Designed for CBR < 5.
  3. No rock excavation. If rock encountered, pricing changes significantly.
  4. Dry season construction (June–September). Productivity factor 1.0.
  5. Private work — no prevailing wages, no performance bonds.
  6. Heavy woods clearing — mature second-growth Douglas fir forest.
  7. Two passing turnouts (40×8 ft each) included in all quantities.
  8. Three cross-drain culverts at low points along alignment.
  9. One-side ditch (uphill side) for full road length.
  10. Aggregate haul ~10 miles from Cottage Grove area quarries.
  11. No stream crossings. If needed, add $5,000–$15,000.
  12. No wetland impacts. If fill required, add permits + mitigation.
  13. Disturbance ~0.51 acre (below 1-acre DEQ 1200-C threshold).

Contingency Justification (15%)

No soil borings yetHigh risk
No topographic surveyMedium risk
No wetland screeningMedium risk
Conservation easement unknownsMedium risk
Tree density unknownLow–Med risk
WeatherLow risk

Next Steps

Complete these items to refine the estimate from AACE Class 4 (−30%/+50%) to Class 3 (−20%/+30%).

  1. Get soil data NRCS Web Soil Survey (free, online, immediate) and hand auger borings at 3–5 locations ($500–$1,000 if DIY)
  2. Walk the alignment Verify terrain, tree density, drainage patterns, wet areas, and access from Cerro Gordo Road
  3. Review conservation easement May impose requirements that affect scope and cost. Get written approval before any disturbance.
  4. Get aggregate quotes Call local suppliers (Knife River, Wildish) for delivered prices to Cerro Gordo Rd
  5. Get contractor quotes Solicit 2–3 bids from local earthwork/road contractors for comparison
  6. Apply for approach permit Lane County Public Works — confirms connection requirements at Cerro Gordo Rd
  7. Run desktop environmental checks NRCS, DOGAMI SLIDO, USFWS IPaC — free screenings, ~2 hours total